While an application to take water over the next ten years is still pending, the developers of Findlay Creek Village have filed yet another short-term application, so they may dig a deep trench to start the final major phase of their development. The application was posted on the EBR web site under EBR # 010-5426….


On December 9, 2007, the Friends of Leitrim Wetland issued a second media release, encouraging the public to object to a new proposal for a Permit To Take Water at Leitrim Wetland that would see 17 million litres of water per day drained from the wetland for the next ten years. This is the equivalent…


On May 20, 2009 the Greenspace Alliance of Canada’s Capital and the Sierra Club Canada filed an application with the Environmental Review Tribunal for Leave to Appeal a 10-year Permit To Take Water issued on April 27, 2009. They also filed a Motion for an Interim Stay. (Supporting the Motion was an Affidavit sworn by…


Appeal of Water Taking Permit at Leitrim Settled On March 23, 2010, the Environmental Review Tribunal accepted a settlement that had been reached between the developers of Findlay Creek Village and the Appellants (the Greenspace Alliance and Sierra Club Canada) acting on behalf of the Friends of Leitrim Wetland. In July 2009, the Tribunal had…


On July 21, 2008, the Ontario Environmental Review Tribunal dismissed a motion by Findlay Creek Properties Ltd.  The motion sought to dismiss an application for Leave to Appeal a permit issued by the Ministry of the Environment to pump water out of Leitrim Wetland.  The appeal is spearheaded by the Greenspace Alliance and the Sierra…